What goes in a turnover package

Last updated 12 August 2026

A turnover package is the argument that the machine was installed correctly, made to somebody who was not there and cannot inspect it. This is what goes in one, in the order it gets read — worked through a single real job rather than described in the abstract.

The contract governs. Scope, format and retention come from your specification. What follows is the shape most precision-maintenance packages take when nobody has specified one, and the order is not arbitrary: it is the order a reviewer actually opens things in.

The job

Project 4118 — overhaul and reinstall P-1201A, an API 610 BB2 crude charge pump on a grouted baseplate, driven by a 700 HP motor through a disc coupling. Wear rings and bearings renewed, baseplate regrouted, aligned to hot targets, vibration accepted to ISO 20816. One machine, one coupling, about forty records.

Small enough to follow end to end, and large enough that every failure mode below has somewhere to hide.

The sections, in the order they get read

#SectionWhat it has to establish
1Cover and indexWhich machine, which job, which revision of the package. A package with no revision on it cannot be superseded, only argued about.
2Equipment registerTag, nameplate data, serials. Everything downstream keys off the tag, so this is the section that makes the rest navigable.
3Procedures and specsWhat the work was checked against, at the revision in force on the day. Not the current revision — the one that governed.
4Instrument calibrationCertificates for every instrument that produced a number in this package. Read early because it can invalidate everything after it.
5Personnel qualificationsWho did the work, and what they were certified to do at the time.
6Foundation and groutProduct, batch, cure conditions, void check and its method. The one check that cannot be repeated once the machine is set.
7Teardown and inspectionWhat came apart, what was found, what the wear pattern indicated, and the disposition of each part.
8Clearances and fitsBearing fits, internal clearance class, wear ring clearance, end play — as-found and as-left against OEM limits.
9Bolt torqueCasing splits, baseplate and anchor bolts, with grade, lubricant, pattern and the calibrated tool.
10Soft foot and shimsAll four feet, the type found, and what went under each — including how many pieces.
11Thermal growth targetsThe cold targets and where they came from. Section 12 is unreadable without this one.
12Shaft alignmentAs-found and as-left, method, instrument, tolerance standard, verdict.
13Run-in and performanceUncoupled solo, coupled, then loaded. Bearing temperatures, process conditions, seal condition.
14VibrationAcceptance readings at every standard point, with the standard and the zone.
15NCRs and RFIsEverything raised, and how each was dispositioned and closed.
16Punch listWhat remains, categorised by whether it blocks startup, blocks handover, or is cosmetic.
17Daily reportsThe narrative. Usually skimmed — and read very closely indeed when something else does not add up.

Sections 11 and 12 are adjacent deliberately. An alignment sheet without its targets in front of it is a page of numbers with no criterion, and a reviewer who has to go looking for the targets will assume they do not exist.

Following one machine all the way through

Take P-1201A and pull its thread. A complete package lets a reviewer do this without asking a single question:

Every one of those lines names the machine, the instrument or product, and the criterion. That is what “traceable” means in practice, and it is why the tag has to be spelled identically in all nine places.

Five ways this package comes back

1. An instrument out of calibration

Wrench TW-004 expires 2026-09-02. If any torque record in the package is dated after that, every reading it produced is void — retrospectively, including ones that passed. This is checked first because it is one date comparison and it can end the review.

Fix: cross-check instrument IDs against calibration expiry before submission, not after.

2. An alignment with no targets

As-left 0.000 on a pump that runs at 300 °F either means the targets were zero — which is wrong — or that the targets exist somewhere and were not included. The reviewer cannot tell which, and the conservative reading is the bad one.

Fix: thermal growth immediately before alignment, with the source of the target named, even when the answer is assumed zero.

3. A verdict with no standard

“Within tolerance” against nothing. OEM, plant precision spec and ANSI/ASA S2.75 disagree, and at 3560 RPM they disagree by enough to change the answer.

Fix: name the document and the row on the sheet itself.

4. A count that does not reconcile

The register lists four machines; there are three sets of alignment records. Either a machine was not aligned or a record is missing, and from outside those look identical. The reviewer has to assume the worse one.

Fix: reconcile section counts against the register before submission. Where something genuinely does not apply, say so explicitly rather than omitting it.

5. Records that contradict each other

A vibration baseline dated the 24th for an alignment completed on the 26th. Somebody typed a date wrong, almost certainly — but the package now says the machine was accepted before it was aligned, and there is no way to tell a typo from a sequence problem after the fact.

Fix: check dates run forward through the package. This is the single most common reason a technically sound job gets returned.

The pass to run before you hand it over

  1. Every instrument ID in the package appears in the calibration section, in date on the day it was used.
  2. Every machine in the register has a record in every section that applies to it, and an explicit note where one does not.
  3. Every alignment has thermal growth targets and a named tolerance standard.
  4. Every torque record has a lubricant and a tool ID.
  5. Every shim record has a piece count, not just a total.
  6. Dates run forward: teardown before fits, fits before alignment, alignment before vibration.
  7. The tag is spelled identically everywhere it appears.
  8. Every NCR is closed, or listed on the punch list as open with an owner.
  9. The package carries a revision, and superseded copies are marked as such.

Nine checks, most of them mechanical. They are worth running as a pass of their own because every one of them is cheap to fix before submission and expensive to fix after — not because of the correction, but because of what a returned package does to the schedule and to the next conversation with that client.

What this page is not

It is not your specification, and it is not a substitute for reading it. Where the contract names sections, formats or retention periods, those govern. This is the shape to start from when nothing has been specified, and the failure modes are the ones worth checking for either way.